Spring 2008 - Spring 2009
Construction of the Green Bay Processing Facility
Summer - Fall 2008
The Fox River Cleanup Group completed a detailed sampling and analysis program to refine the limits of selected areas scheduled for dredging in 2009. This program was extended through fall 2008 to areas of the river scheduled for dredging in subsequent years.
January 2009
The Fox River Cleanup Group submitted to the EPA and WDNR the Pre-Final Design (90%) for cleanup work to be performed from 2010 to completion.
April 28, 2009
Dredging operations begin
Summer 2009
Capping and sand covering operations begin.
Mid-November 2009
First year of operations conclude. Dredging and processing exceed 2009 targets.
April 5, 2010
Dredging resumes on the lower Fox River
September 2010
The Fox River Cleanup Project tops 700,000 work hours without a lost time incident (total does not include hours for transportation of sediment to the landfill).
November 13, 2010
Dredging and processing operations conclude for 2010. Second year operations exceed target goals every week of operations.
April 18, 2011
The third year of dredging and processing begins.
May 2, 2011
Capping and covering operations resume.
August 2011
Dredging and processing conclude for the season.
October 31, 2011
Capping and covering operations conclude for the 2011 season.
May 2012
Operations resume for the 2012 season.
November 2012
Dredging and processing conclude for the season.
April 2013
Dredging and processing operations resumed in OU4 on April 1, 2013.